Completion Delayed On East Link Light Rail At Least One Year

East Link Light Rail
Photo Credit: Sound Transit

The Sound Transit Board System Expansion Committee recently received a detailed briefing on continuing efforts to identify new opening dates for current Link construction projects, including the East Link project. According to the release, “While the East Link extension was planned to open in mid-2023, construction challenges are currently projected to delay the completion by at least a year.”

Since April, Sound Transit has been flagging delays affecting not only the East Link project but also the Downtown Redmond, Lynwood, and Federal Way Link projects.

“Within about the next four years, our carbon- and congestion-free light rail system will more than double from 26 to 62 miles and from 25 to 50 stations,” said Sound Transit Interim CEO Brooke Belman. “While we are on a path to fully resolve impacts of COVID-19, the concrete delivery strike and our construction challenges, we have more work to do before we can reliably establish opening dates. We will work tirelessly with our contractors to complete these extensions as rapidly as possible without compromising on safety or quality.”

The issues that East Link have been facing include construction quality and durability concerns with raised concrete structures (plinths) that support the tracks in key sections of the alignment.

Sound Transit has been analyzing concerns related to pre-cast concrete plinth blocks on the bridge segment. It has recently been reported that preliminary investigation results during July and August suggest that while some of the blocks have hairline cracks, the blocks do not need to be replaced.

There have been more issues on both the east and west sides of the bridge with cast-in-place concrete plinths supporting the tracks. There are issues with mortar pads, rebar placements and track fasteners, which the contractor has agreed to fix by re-casting the plinths to ensure the long-term reliability and safety of the extension.

According to the release, continuing work is required to identify new project opening timelines for the four projects, which must include time for activation work once construction is complete. Sound Transit will continue to assess the work being done with the light rail to identify a new completion date.

Hot this week

Bellevue’s Wish List…

Downtown Bellevue has had an influx of new stores...

4.22-Acre Mixed-Use Development Approved in Downtown Bellevue

A major mixed-use residential development in downtown Bellevue has...

Bellevue Tip Leads to Conviction in Multi-State Sex Trafficking Case

A federal sex trafficking case that began with a...

Blazing Bagels Closes All Locations, Including Bellevue

Blazing Bagels has closed all of its locations, including...

Adrian’s Restaurant & Tequila Bar in Old Bellevue Closes Abruptly

Adrian’s Restaurant & Tequila Bar has closed abruptly, according...
Home Comfort Alliance 300 x 250 - March 2026

Copper Kettle Coffee Bar to Close January 3 at Bellevue Botanical Garden

Copper Kettle Coffee Bar, the coffee counter inside the...

Former Downtown Bellevue Rite Aid Site Approved for 19-Story Office Tower

The City of Bellevue has given Design Review approval...

Seattle’s Transform 180 to Open First Eastside Gym in Downtown Bellevue on Jan. 1

Transform 180, an owner-run training club with three gyms...

Holiday Traditions Carry On with The Bellevue Collection

The holidays are filled with many traditions, from Thanksgiving...

Brazilian Restaurant Bar da Vila to Open Nov. 18 in Old Bellevue

Bar da Vila, a new Brazilian restaurant, will open...

Jocovine Closes in Old Bellevue as Realogics Sotheby’s Seeks New Concept

Jocovine, the bistro that operated in the front of...

Garden d’Lights Returns to Bellevue Botanical Garden Nov. 28

Garden d’Lights returns to the Bellevue Botanical Garden on Saturday, November...

Related Articles

Popular Categories

Home Comfort Alliance - Banner 728 x 90 for HVAC