Completion Delayed On East Link Light Rail At Least One Year

East Link Light Rail
Photo Credit: Sound Transit

The Sound Transit Board System Expansion Committee recently received a detailed briefing on continuing efforts to identify new opening dates for current Link construction projects, including the East Link project. According to the release, “While the East Link extension was planned to open in mid-2023, construction challenges are currently projected to delay the completion by at least a year.”

Since April, Sound Transit has been flagging delays affecting not only the East Link project but also the Downtown Redmond, Lynwood, and Federal Way Link projects.

“Within about the next four years, our carbon- and congestion-free light rail system will more than double from 26 to 62 miles and from 25 to 50 stations,” said Sound Transit Interim CEO Brooke Belman. “While we are on a path to fully resolve impacts of COVID-19, the concrete delivery strike and our construction challenges, we have more work to do before we can reliably establish opening dates. We will work tirelessly with our contractors to complete these extensions as rapidly as possible without compromising on safety or quality.”

The issues that East Link have been facing include construction quality and durability concerns with raised concrete structures (plinths) that support the tracks in key sections of the alignment.

Sound Transit has been analyzing concerns related to pre-cast concrete plinth blocks on the bridge segment. It has recently been reported that preliminary investigation results during July and August suggest that while some of the blocks have hairline cracks, the blocks do not need to be replaced.

There have been more issues on both the east and west sides of the bridge with cast-in-place concrete plinths supporting the tracks. There are issues with mortar pads, rebar placements and track fasteners, which the contractor has agreed to fix by re-casting the plinths to ensure the long-term reliability and safety of the extension.

According to the release, continuing work is required to identify new project opening timelines for the four projects, which must include time for activation work once construction is complete. Sound Transit will continue to assess the work being done with the light rail to identify a new completion date.

Hot this week

4.22-Acre Mixed-Use Development Approved in Downtown Bellevue

A major mixed-use residential development in downtown Bellevue has...

Bellevue Tip Leads to Conviction in Multi-State Sex Trafficking Case

A federal sex trafficking case that began with a...

Blazing Bagels Closes All Locations, Including Bellevue

Blazing Bagels has closed all of its locations, including...

Adrian’s Restaurant & Tequila Bar in Old Bellevue Closes Abruptly

Adrian’s Restaurant & Tequila Bar has closed abruptly, according...

Salt & Straw Ice Cream Opens in Bellevue April 24 with Giveaways and Events

Salt & Straw will open a new scoop shop...
Home Comfort Alliance 300 x 250 - March 2026

Bellevue Police to Fly Drones to Emergency Calls Before Officers Arrive

Bellevue police will begin flying drones to emergency scenes...

Now Selling: A Rare Park-Front Address In The Heart of Bellevue

In great cities around the world, homes bordering celebrated...

Bellevue Seeks Drivers to Test Crosswalk Alert App, Pays $100

The City of Bellevue is looking for local drivers...

Four-Building Redevelopment of Panera Bread Strip Mall Advances in Downtown Bellevue

The east half of Bellevue North, the four-building redevelopment...

Related Articles

Popular Categories

Home Comfort Alliance - Banner 728 x 90 for HVAC