Amazon Announces Pause on 6 Bellevue Towers to Rethink Workspace Design

Artise on 106th Ave NE
Artise on 106th Avenue NE

Amazon recently announced that they will be pausing construction on six of their office towers in Bellevue.

The six towers total more than three million square feet of space. One tower’s construction is immediately halted, Bellevue 600’s second tower, while the other five’s exterior shell and core work will be completed, according to Puget Sound Business Journal.

The tech company plans to complete the exterior core and shell, as well as lobby floors, communal areas, and retail space on the following towers; Tower 1 at Bellevue 600, 555 Tower, towers 2 and 3 at West Main, and The Artise.

The decision to pause construction does not affect hiring, According to Amazon. They are still fulfilling their pledge to have over 25,000 employees in Bellevue.

Amazon currently has almost 10,000 employees, with 2,000 open roles in Bellevue. They will continue to invest and engage with the community despite their pause on construction.

Amazon’s vice president of global real estate and facilities, John Schoettler, said that “The pandemic has significantly changed the way people work. For our corporate and tech roles, we’ve adopted a hybrid model that offers employees increased flexibility – each team decides the balance between in-office and remote work that makes sense for them. It’s early days and like many companies, we’re still learning how these new habits may impact our office footprint. Our offices are long-term investments and we want to make sure that we design them in a way that meets our employees’ needs in the future. As we continue to learn, we’re pausing construction to reevaluate the design of some of our projects in Bellevue. This doesn’t affect our plans to bring more than 25,000 jobs to the city, or our commitment to continuing to invest in and engage with the community—including providing affordable housing and supporting local nonprofits.”

At this time, it us unknown how long this pause on completing construction will last. They explained that they are taking their time to get the final product right as working from home has become more prominent since the pandemic.

Hot this week

4.22-Acre Mixed-Use Development Approved in Downtown Bellevue

A major mixed-use residential development in downtown Bellevue has...

Bellevue Tip Leads to Conviction in Multi-State Sex Trafficking Case

A federal sex trafficking case that began with a...

Blazing Bagels Closes All Locations, Including Bellevue

Blazing Bagels has closed all of its locations, including...

Adrian’s Restaurant & Tequila Bar in Old Bellevue Closes Abruptly

Adrian’s Restaurant & Tequila Bar has closed abruptly, according...

Salt & Straw Ice Cream Opens in Bellevue April 24 with Giveaways and Events

Salt & Straw will open a new scoop shop...
Home Comfort Alliance 300 x 250 - March 2026

Route 550 Bus to End Service Aug. 29 as 2 Line Takes Over Bellevue-Seattle Trips

The Route 550 bus, which has carried riders across...

TikTok to Lay Off 75 Employees at Its Downtown Bellevue Office

TikTok will cut 75 jobs at its downtown Bellevue...

Style Code Consultations Return to Bellevue Square With 1:1 Stylist Sessions Sept. 17-20

Bellevue Square is bringing back its Style Code Consultations...

Fashion Runway Show Set for Sept. 26 at KidsQuest’s Future Downtown Bellevue Home

The Bellevue Collection will host its Fashion Reigns Runway...

Activists in ‘Rogue AI Agent’ Costumes Disrupt OpenAI’s Downtown Bellevue Office

Demonstrators dressed as "rogue AI agents" ran through the lobby of OpenAI's City Center Plaza office Friday morning in a protest against the company's $500 billion Stargate data center expansion.

Itadaki Yakiniku Closes at The Bellevue Connection

Itadaki Yakiniku, the Japanese steakhouse at The Bellevue Connection,...

Bellevue Wants Your Input on $1.5 Billion in Unfunded Transportation Projects

Bellevue has identified roughly $1.5 billion in transportation projects...

Related Articles

Popular Categories

Home Comfort Alliance - Banner 728 x 90 for HVAC